Reference pricing for a turnkey install on a lot with no power equipment at all—from a new grid connection to the chargers themselves. Here are three representative configurations.
Reference pricing | Tax excludedAll figures are reference prices for installations in Japan, quoted in Japanese yen.
First, the premise
This is not an invitation to invest
Installing chargers does not guarantee a profit. A-Charge is the intake system for a facility that has already decided to spend on bays or chargers, so it can run them at low cost. Yield is a number the owner calculates and takes responsibility for. After that decision, we help run the site cheaply.
Look at I-S3’s electrical construction and monitoring systems—not at how many A-Charge billing sites exist yet. A-Charge is the parking OS built on that work.
High-voltage interconnection, self-consumption, repowering, and O&M. Food-plant ~200 kW self-consumption and high-voltage ~500 kW upgrades: live sites, multiple stakeholders, electrical work done safely.
Remote solar monitoring and 30-minute demand sizing, our own RightOS anonymous queue, and an OCPP 1.6 / 2.0.1 central system with load sharing under the site power cap. Not spreadsheets bolted on after the fact.
Hundreds of jobs centered on Gunma. Mostly AC (Tesla Wall Connector and similar); over 99.9% of residential jobs finish the same day. Eleven prefectures by our own visits, six in Kansai via partners (17 total). We also design turnkey facility packages that include 50 kW / 120 kW DC.
Billing sites under the A-Charge name are still being added. Installing, isolating, monitoring, and reconnecting electrical plant is I-S3’s core work.
EV installation record | Customer stories | Primary field notes
Send us the charger model and we will confirm compatibility.
The first step to whole-lot coverage. Hotels, retail, monthly parking.
| Item | Reference price (tax excl.) |
|---|---|
| AC chargers × 10 | ¥2,200,000 |
| System setup | ¥1,000,000 |
| Electrical work (incl. new grid connection) | ¥2,000,000 |
For short-stay sites and lots along major roads.
| Item | Reference price (tax excl.) |
|---|---|
| 50 kW DC fast charger × 1 | ¥2,900,000 |
| System setup | ¥100,000 |
| Electrical work (incl. new grid connection) | ¥3,200,000 |
A full-scale charging hub. High-voltage cubicle leaves room to grow.
| Item | Reference price (tax excl.) |
|---|---|
| 120 kW DC fast charger × 1 | ¥5,000,000 |
| AC chargers × 10 | ¥2,200,000 |
| High-voltage cubicle | ¥8,000,000 |
| System setup | ¥1,100,000 |
| Electrical work (incl. utility pole installation) | ¥3,500,000 |
Send us the address and your preferred configuration. We will check grid-connection feasibility and reply with an estimate.